We would like to keep you informed about the production stops of our suppliers.
We as ISOPARTNER Netherlands will increase our stocks to accommodate this as much as possible. In order to keep this on track, we would also like to ask you to take into account the projects that are taking place around these times.
Isover production halt
A furnace will be replaced in Etten Leur, resulting in a shutdown of the plant for a period of approximately 10 weeks. The planned work will take place from July 1, 2024 to September 10, 2024. This will impact the following products:
- Isover CLIMLINER Slab 602 / 302
- Isover TECH Loose Wool
- Isover TECH Slab 2.0
- Isover InsulSafe Plus Wood
For deliveries to take place during this period, we need your order by May 31, 2024.
Paroc production line maintenance extension
The production stop for the Paroc Pro Lamella Mat (50kg/m3) was scheduled until June 3, 2024. However, we have been informed that the production stop will be extended by 3 weeks. As a result, the new startup is now scheduled for June 24, 2024.